After Buying a Machine From Overseas: Arranging Installation, Training, and Remote Support
The Real Work Starts After the Machine Reaches Port
Food machines such as encrusting machines and dividers are test-run at the factory in Taiwan before shipment. But crating, shipping, customs clearance, inland transport, and moving into the customer's plant involve vibration, temperature and humidity changes, and reconnecting power, all of which can leave the machine in a different state than when it left the factory. Add the customer's own dough recipes, filling consistency, and room temperature, all different from the test run, and the real goal of overseas installation and training is "getting the machine to produce acceptable products with the customer's ingredients and environment."
Three Common Approaches to Overseas Installation
1. The manufacturer sends a technician on site: The technician travels abroad with tools and common parts and handles positioning, power connection, test runs, adjustment, and operator training. This gives the best results, but requires arranging visas, flights, accommodation, and local transport, and timing has to fit shipping schedules and customs clearance. These costs are usually charged separately, and the contract should clearly state who pays, how many technician days are included, and how extra days are charged.
2. Installation by a local partner: A distributor or affiliated machinery technician in the customer's country installs the machine under the manufacturer's guidance. Response is fast and communication is easy, provided the local partner is familiar with this kind of machine.
3. Customer self-installation + remote guidance: Common when the machine isn't complicated and the customer has in-house mechanical and electrical staff. The manufacturer provides installation instructions, electrical diagrams, and checklists in advance, and guides the installation live by video on the day.
Which one to choose depends on the model's complexity, the customer's in-house technical capability, and the budget. Arrangements for a small tabletop machine and a complete production line can be very different.
What Video Training Can Do
Video is well suited to:
- Checking accessories and parts item by item after unpacking
- Guiding checks of voltage, phases, frequency, and grounding before connecting power
- Demonstrating the control panel and adjusting unit weight and speed
- Looking at how products are formed to judge whether the dough or filling consistency is right
- Demonstrating the order of disassembly, washing, and daily maintenance
But it has limits: abnormal mechanical noise, vibration, and temperature have to be described by people on site; areas the camera can't see can only be filmed after the customer opens them up; and time differences slow down real-time responses. A stable internet connection, a phone or tablet that can be mounted, good lighting, and someone on site who understands the operating language will make remote support much more effective.
Safety reminder: For any disassembly, cleaning, or adjustment guided by video, first stop the machine and cut the power, lock out and tag out if necessary, and confirm the machine has completely stopped before starting. Never put hands into conveying, extruding, or cutting areas while they're running.
How to Ship Parts
There are usually two ways to ship parts overseas:
- International express courier: For small parts of a few kilograms, door-to-door and fast, but shipping is more expensive, and some countries require the recipient to provide a tax ID or file an import declaration.
- With the next shipment by sea or air freight: Suitable for non-urgent or large parts.
Include a commercial invoice when shipping parts, clearly stating the description, model, quantity, and value, to avoid getting held up in the importing country. For food-contact parts (such as nozzles and forming molds), if the importing country has food contact material rules, material certificates may also be required; see EU food contact material rules.
The most efficient approach is to buy a recommended set of common wear parts with the machine and keep them at the customer's plant, so a broken part can be replaced first and restocked afterward, minimizing downtime. For which parts to stock, see What Export Customers Ask About Manuals, Parts, and Warranty.
What to Agree On Before Ordering
- Who performs the installation, how it's charged, and how many days are included
- Who prepares the ingredients for the test run (usually the customer's own ingredients)
- Who is trained and for how many hours, and whether written or video materials on operation and cleaning are provided
- The contact person, available hours, and language for remote support
- Who pays shipping and import duties for parts
For Dong-Yih Machinery's overseas service arrangements and related costs, please call 06-257-4644 or reach us through our contact information page.
FAQ
Q: We bought a machine from abroad. Who installs it?
A: Three common options: the manufacturer sends a technician, a local partner installs it, or the customer installs it with video guidance from the manufacturer. The actual approach and costs should be agreed before ordering.
Q: Can training be done by video only?
A: Yes, when the machine is relatively simple and the customer has in-house mechanical and electrical staff; video is good for guiding unpacking, pre-connection checks, operation, and cleaning. Problems such as abnormal noise or vibration still need on-site staff to describe and film them.
Q: What's the fastest way to get a replacement part?
A: Small parts are mostly sent door-to-door by international express courier with a commercial invoice. The biggest time-saver is keeping common wear parts at the plant from the start.
Q: What should we watch for when disassembling under video guidance?
A: Stop the machine and cut power first, lock out and tag out if necessary, and confirm the machine is completely still before disassembling. Never put hands into forming or cutting areas while they're running.